This guide sets out a specification workflow for engineers, contractors and buyers: start with the lighting requirement, collect the site data, choose the configuration, size the energy system, and prepare the documents a supplier must provide. The order matters. The lighting and site requirements come first, the product form factor second, and component sizing third.
Before comparing any product, establish what the road is required to achieve. That requirement comes from a lighting standard or the authority's specification, and it is the starting point for every later decision.
Take the requirement from the target country's standard and the project specification, with a lighting engineer's input where the project calls for one. Ask suppliers for photometric data for the fitting, such as IES or LDT files, so that the design can be calculated. Do not assume that a light meets a lighting class without a calculation for your layout, and do not specify a road's illuminance from the light's wattage.
(1).png)
| Project brief item | Source | Confirmed |
|---|---|---|
| Road type and classification | Authority or project documents | |
| Vehicle and pedestrian use | Design brief | |
| Required lighting performance and uniformity | Target-country standard or specification | |
| Photometric data for the fitting | Supplier (IES or LDT files, if available) | |
| Who is responsible for the design calculation | Contract documents |
The same fitting performs differently on different roads. Collect the site data that the lighting design and the energy sizing both depend on.
| Site input | Why it matters | Source |
|---|---|---|
| Road width and number of lanes | Determines what the lighting has to cover | Drawings |
| Pole height, arm and setback | Affects light distribution and the fitting's mounting | Project design |
| Pole spacing | Set by the photometric calculation and the standard | Lighting design |
| Obstructions and shading | Trees, buildings and structures can block the panel or the light | Site survey and photos |
| Orientation | Panel aiming depends on the road direction and the site | Site survey |
| Wind exposure | Affects the pole, arm and panel loading | Site data and supplier pole data |
| Foundation conditions | Affects the pole base design | Geotechnical or site information |
| Maintenance access | Determines how units will be serviced | Site survey |
Do not take a pole height or spacing from one project and apply it to another. Both depend on the photometric data, the road layout and the local standard. Lighting colour or colour temperature, where it is specified, also follows the authority's requirement.
Regional conditions change the details. For climate, standards and project context, see the regional guides: solar street lighting project requirements in Africa and solar street lighting for Thailand projects.
The architecture of the light changes installation, servicing and sizing limits. Among solar street lights for road projects, the two common forms are all-in-one units, where the panel, battery and light are integrated in one body, and split systems, where the panel and battery are separate from the fitting. Neither is more reliable or cheaper in every case.
Use the matrix below to start the conversation with a supplier. It describes what to consider and does not name a winner.
| Consideration | All-in-one may suit when… | Split may suit when… |
|---|---|---|
| Installation | A single integrated unit simplifies work at height | Separate mounting of components is acceptable |
| Panel orientation | The site and pole layout allow the unit to face a suitable direction | The panel needs to be aimed or positioned independently of the light |
| Size of energy system | The required panel and battery fit within the unit | The design needs more panel or battery capacity than an integrated unit can hold |
| Service access | Servicing the integrated unit is workable for the maintenance team | Separate components are easier to reach or replace |
| Theft and tamper risk | The unit's security arrangement is judged adequate | The location of components and their securing suits the site |
Ask the supplier which configurations it currently offers and request the documents for the exact model, not for the architecture in general.
.png)
Energy sizing connects the lighting requirement to the panel and battery. Wattage alone does not do it.
A supplier's sizing should be traceable to its inputs. At a simplified level, the logic runs like this:
This is a simplified outline, not a design method. The supplier's calculation for the exact model and site is what you should review. Ask what each input is.
| Input to confirm | Source |
|---|---|
| LED power and dimming profile | Exact SKU datasheet and the project's operating requirement |
| Night operating hours | Project requirement and location |
| Solar resource in the worst month | Target-site data |
| Usable battery energy | Exact SKU datasheet |
| Panel size and orientation | Exact SKU datasheet and site survey |
| Backup days required | Project requirement |
| Temperature range and system losses | Site data and supplier assumptions |
A system that performs well in a sunny season can fall short in the worst month. Ask the supplier to show how the design behaves if the solar resource is lower than assumed, or if the lamp runs longer than planned. Do not accept a general promise about operation through rainy periods without the underlying assumptions. Backup days are a project requirement tied to the site, not a universal number.
Before approving a supplier, decide which documents must accompany the bid. Not every record will exist for every model, so ask for the ones your tender requires and confirm which model each one covers.
Typical items to request:
| Document | What to check | Status |
|---|---|---|
| Photometric file or calculation | Matches the fitting offered and your layout | |
| Datasheet | Current revision of the exact model | |
| Pole and wind data | Suits the site's wind exposure | |
| Electrical diagram | Matches the configuration offered | |
| Battery and panel details | Consistent with the sizing calculation | |
| Reports and certificates | Cover the exact model and the tender's requirement | |
| Warranty and manuals | Duration, scope and exclusions written down |
Share location, road width and length, pole height, desired operating hours, backup days and any lighting or tender standard. We'll review which product configuration may fit. You can request a road lighting project quotation and include the lighting class and autonomy requirements with your enquiry.
No. The light distribution, the pole height and spacing, the operating profile, the power sizing and the local criteria all matter. Wattage alone does not tell you how a road will be lit.
Compare panel orientation, size constraints, installation and service access for your site. There is no universal winner.
The project requirement and the site's solar resource decide. Calculate it using a defined worst-period design assumption and ask the supplier to show the inputs.
Photometric data such as IES files where available, a wiring diagram, pole and mounting data, the datasheet, and the warranty and certification documents your tender requires.